THE PARTNERSHIP TMA ROADWORK UPDATE FOR

THE WEEK OF AUGUST 21 2017

 

 

REMINDER: IT’S ILLEGAL AND UNSAFE TO STOP ON ROADWAY TO SEE THE ECLIPSE TODAY

 

This short article from the Pittsburgh Post-Gazette has some tips on how to drive safely during today’s solar event:

 

http://www.post-gazette.com/news/transportation/2017/08/19/Tips-for-safe-driving-during-the-solar-eclipse-nbsp/stories/201708190080

 

Tips of the Week

 

  • On August 21, the following lane closures are scheduled for Perkiomen Twp for bridge inspections:

 

-- 8:00am – 11:00am, Schwenksville Rd between PA 29 (Main St) and Park Ave

 

-- 11:00am – 2:00pm, westbound Rt 73 (Skippack Pk) between PA 29 (Main St) and Haldeman Rd

 

 

  • Through August 21, PA 29 (Main Street) in East Greenville Twp will have lane closures between Church St and Front St from 9:00am – 3:00pm for utility installation.

 

 

  • From August 21 – 22, PA 152 (Limekiln Pk) in Upper Dublin Twp will have lane restrictions with flaggers between Fort Washington Ave and Bell Lane from 9:00am – 3:00pm for tree removal.

 

 

  • From August 22 – 25, Business US 202 (Doylestown Rd) in Montgomery Twp will have lane restrictions with flaggers between Meadow Glen Rd and Country Club Dr from 9:00am – 3:00pm for tree removal.

 

 

  • On August 24, northbound US 202 (Dekalb Pike) in Lower Gwynedd Twp will have lane restrictions between School House Ln and Sumneytown Pk from 9:00am – 3:00pm for tree removal.

 

 

  • From August 24 – 31, Dreshertown Rd in Upper Dublin Twp will have lane closures between Caras Ct and Crestview Dr from 9:00am – 3:00pm for utility installation.

 

 

  • Through August 31, Route 113 (Harleysville Pk/Main St) in Franconia Twp will have lane restrictions overnight between Sumneytown Pk (Route 63) and Broad St from 7:00pm – 5:00am for milling & paving.

 

 

  • Through August 2017, Layfield Rd in Upper Hanover Twp will have 24-HOUR CLOSURE between Kutztown Rd and Schoolhouse Rd for bridge rehabilitation.

 

 

  • Through Sept 10, Orvilla Rd in Hatfield Twp will be CLOSED & DETOURED between County Line Rd and Cowpath Rd from 7:00pm – 5:00am for utility installation.

 

 

  • Through September 30, PA 63 (Welsh Rd) in Upper Dublin and Upper Moreland Twps will have lane closures between Twining Rd and Computer Ave from 9:00am – 3:30pm for deck rehabilitation.

 

 

  • Through October 2017, Limekiln Pk (PA 152) in Horsham, Montgomery & Warrington Twps will be CLOSED & DETOURED 24 HOURS between County Line Rd and Westminster Dr for utility installation and paving. 

 

 

  • Through October 2017, Plank Rd in Perkiomen Twp will have 24-HOUR CLOSURE between PA 29 (Gravel Pk) and PA 73 (Skippack Pk) for excavation and paving work.

 

 

  • Through November 1, PA 63 (Main St) in Lower Salford Twp will have lane restrictions between PA 113 (Harleysville Pk) and Carrie Ln from 9:00am – 3:00pm for roadway and culvert work.

 

 

  • Through September 2018, County Line Rd in Montgomery, Horsham, & Warrington Twps will have lane restrictions between East Kulp Rd & Stump Rd from 7:00am – 3:00pm for utility installation.

 

 

  • Through May 2019, Otts Rd in Perkiomen Twp between Miller Rd and PA 29 (Gravel Pike) will have 24-HOUR CLOSURE for excavation and paving work.

 

 

Please find below a listing for all PennDOT roadwork projects in Bucks and Montgomery Counties:

 

BUCKS COUNTY

 

 

US 13 North (Bristol Pike), Bensalem Twp.

ITS Fiber Installation: LANE CLOSURE between Black Lake Run & PA 63 (Woodhaven Rd.).  7 PM - 5 AM.

8/11/17

Oxford Valley Rd., Falls, Lower Makefield, Middletown twps.

Bridge Rehabilitation: CLOSED & DETOURED between I-95 & Stoney Hill Rd. Interchanges.  9 PM - 6 AM.  DETOUR POSTED.

8/13/17-8/18/17

PA 63 E & W (Woodhaven Rd.) ramps to I-95 N & S, Bensalem Twp.

Surface Treatment: RAMP CLOSED & DETOURED.  7 PM - 5 AM.  DETOUR POSTED.

8/13/17-8/18/17

*I-95 N & S ramps to PA 63 E & W (Woodhaven Rd.),  Bensalem Twp.

Surface Treatment: RAMP CLOSED & DETOURED.  7 PM - 5 AM. DETOUR POSTED.

8/13/17-8/18/17

Taylorsville Road, Lower Makefield Twp.

Survey Work: LANE CLOSURES between Woodside Road and Highland Drive. 12 AM - 6 AM.

8/14/17

Woodside Road, Lower Makefield Twp.

Signal Layouts:  ALTERNATING TRAFFIC between River Road and Taylorsville Road. 12 AM - 6 AM.

8/14/17

*I-95 South, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between PA 332 (Yardly-Newtown Rd.) & NJ State line.  12 AM - 2 PM.

8/14/17

*I-95 North, Lower Makefield Twp.

Barrier Installation: LANE CLOSURE between PA 332 (Yardley-Newtown Rd.) & NJ State line.  12 AM - 6 AM.

8/14/17

*I-95 South, Lower Makefield Twp.

Barrier Installation: RIGHT LANE CLOSED between NJ state line & PA 332 (Yardley-Newtown Rd.).  8 PM - 2 PM.

8/14/17-8/18/17

Buck Rd., Lower Southampton, Northampton twps.

Milling & Paving: LANE RESTRICTIONS between Bridgetown Pike/Jay St. & Rocksville Rd.   7 PM - 5 AM.

8/14/17-8/18/17

*I-95 N & S, Bensalem Twp.

Milling & Bridge Repair: INTERMITTENT  LANE CLOSURES between New Falls Rd. & Newtown Yardley Rd. Interchange.  7 PM - 5 AM.

8/14/17-8/18/17

PA 309 N & S, Hilltown, Rockhill twps.

Surveying: LANE CLOSURES between Church Rd. & Rich Hill Rd.  9 AM - 3 PM.

8/14/17-8/18/17

PA 611 South, Doylestown Twp., Doylestown Bor.

Line Painting: RIGHT LANE CLOSED between N. Broad St. & W. State St.  9 AM - 3 PM.

8/14/17-8/18/17

PA 611 (Easton Rd.), Warrington Twp.

Curb Ramp Installation:  LANE CLOSURES at Steeplechase Drive; Turk Rd.; Almshouse Rd.; Edison Furlong Rd.;  New Britain Rd./Sauerman Rd.; Bristol Rd.; Kelly Rd.; Freedoms Way/Oxford Drive; Doylestown Plaza.  9 AM - 3 PM.

8/14/17-8/18/17

*I-95 North, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between PA 332 (Yardley-Newtown Rd.) & NJ State line.  10 AM - 6 AM.

8/14/17-8/18/17

*I-95 South, Lower Makefield Twp.

Barrier Installation: RIGHT SHOULDER CLOSED between PA 332 (Yardley Newtown Rd.) & NJ State line.  24-HOUR CLOSURE.

8/14/17-8/20/17

*I-95 North, Lower Makefield Twp.

Barrier Installation: RIGHT SHOULDER CLOSURE between PA 332 (Yardley-Newtown Rd.) & NJ State line.  24-HOUR CLOSURE.

8/14/17-8/20/17

PA 263 (York Rd.), Warminster Twp.

Milling & Paving: LANE CLOSURE between County Line Rd. & Tennyson Drive.  Weeknights.  7 PM - 5 AM.

8/14/17-9/15/17

PA 32 (River Road), Tinicum Twp.

Survey Work: LANE RESTRICTIONS between Woodside Rd. & I-95. 7 AM - 4 PM

8/14/17-8/21/17

Taylorsville Road, Lower Makefield Twp.

Survey Work: LANE CLOSURES between Woodside Road and Highland Drive. 10 AM - 6 AM.

8/14/17-8/21/17

Hulmeville Rd., Middletown Twp.

Utility Installation: CLOSED & DETOURED between Old Lincoln Hwy. & Richardson Ave.  Weekdays.  9 AM - 3 PM.  DETOUR POSTED.

8/14/17-8/23/17

Ridge Rd., East Rockhill Twp.

Pipe Replacement: CLOSED & DETOURED between PA 313 (Dublin Pike) & Old Bethlehem Rd.  8 AM - 3 PM.  DETOUR POSTED.

8/16/17-8/17/17

Oxford Valley Rd., Falls, Lower Makefield, Middletown twps.

Bridge Rehabilitation: LANE CLOSURES between Big Oak Rd. & Cabot Blvd.   9 PM - 6 AM.

8/16/17-8/18/17

Bristol Pike, Bensalem Twp.

ITS Structure & DMS Re-Installation: LANE CLOSURE between Black Lake Run & PA 63 (Woodhaven Rd.).  6 PM - 5 AM.

8/18/17

*I-95 North, Bensalem Twp.

ITS DMS Commissioning: SHOULDER CLOSURE between PA 63 (Woodhaven Rd.) & PA 132 (Street Rd.).  9 PM - 5 AM.

8/17/17-8/18/17

*I-95 South, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between NJ state line & PA 332 (Yardley-Newtown Rd.)   8 PM - 10 AM.

8/18/17-8/19/17

*I-95 North, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between PA 332 (Yardley-Newtown Rd.) & NJ State line.  10 AM - 11 AM.

8/18/17-8/19/17

*I-95 North, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between PA 332 (Yardley-Newtown Rd. & NJ state line.   6 PM - 12 PM.

8/19/17-8/20/17

*I-95 South, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between NJ state line & PA 332 (Yardley-Newtown Rd.)   7 PM - 11 AM.

8/19/17-8/20/17

*I-95 North, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between PA 332 (Yardley-Newtown Rd. & NJ state line.   6 PM - 6 AM.

8/20/17-8/21/17

*I-95 South, Lower Makefield Twp.

Barrier Installation: LANE CLOSURES between NJ state line & PA 332 (Yardley-Newtown Rd.)   6 PM - 2 PM.

8/20/17-8/21/17

E. State Rd., Doylestown Bor.

Utility Installation: LANE CLOSURE between East St. & Boro Mill Hill Rd.  Weekdays.  9 AM - 3 PM.

8/21/17-8/28/17

Radcliffe St., Bristol Bor.

Utility Installation: LANE CLOSURE between Taylor St. & Pine Grove St.  Weekdays.  9 AM - 3 PM.

8/21/17-8/28/17

Hulmeville Rd., Bensalem Twp.

Utility Installation: LANE CLOSURE between Buckingham Drive & Lynnbrook Drive.  Weekdays.  9 AM - 3 PM.

8/23/17-8/30/17

Bridgetown Rd., Northampton Twp.

Utility Installation: LANE CLOSURE between E. Bristol Rd. & Mapleview Drive.  Weekdays.  9 AM - 3 PM.

8/23/17-8/30/17

PA 63 (Woodhaven Rd.), Bensalem Twp.

Milling & Paving: LANE RESTRICTIONS between Bristol Pike & I-95.  7 PM - 5 AM.

8/6/17-8/11/17

Swamp Rd., Wrightstown Twp.

Surface Treatment: LANE RESTRICTIONS between Sacketts Ford Rd. & Apple Hill Rd.  Weekdays.  9 AM - 3 PM.  Saturday. 7 AM - 5 PM.

8/7/17-8/12/17

New London Rd., Franklin Twp.

Surface Treatment: LANE RESTRICTIONS between at Appleton Rd.  Weekdays.  9 AM - 3 PM.  Saturday.  7 AM - 5 PM.

8/7/17-8/12/17

*I-95 North, Middletown Twp.

Milling & Bridge Deck Repairs: INTERMITTENT LANE CLOSURES between PA 413 & US 1 Interchanges.  7 PM - 5 AM.

8/7/17-8/13/17

Woodside Road, Lower Makefield Twp.

Survey: ALTERNATING TRAFFIC between River Road and Taylorsville Road. 10 AM - 6 AM.

8/7/17-8/13/17

Kumry Rd., Milford Twp.

Base Repair: CLOSED & DETOURED between PA 663 & Allentown Rd.  Weekdays.  7 AM - 5 PM.  DETOUR POSTED.

8/7/17-8/18/17

South State St., Newtown Bor.

Utility Installation: CLOSED & DETOURED between Penn St. & Washington Ave.  Weekknights.  9 PM - 6 AM.  DETOUR POSTED.

7/30/17-9/15/17

Loux Covered Bridge over Cabin Run on Carver-Wismer Road, Bedminster Township

CLOSED & DETOURED INDEFINITELY: Due to structural damage sustained from an oversized vehicle DETOUR POSTED

8/1/17-Indef.

*US 1 N & S, Middletown Twp.

Shielding/Formwork Installation: INTERMITTENT LANE CLOSURES at Woodbourne Rd. & Oxford Valley Rd.  7 PM - 5 AM.

8/3/17-8/6/17

PA 413 (New Rodgers Rd.), Bristol Twp.

Bridge Rehabilitation: CLOSED & DETOURED between Plumbridge Drive & Bath Rd./Durham Rd.  8 PM - 5 AM.  DETOUR POSTED.

7/16/17-8/18/17

PA 413 (New Rodgers Rd.), Bristol Twp.

Bridge Rehabilitation: LANE RESTRICTIONS & 15-MINUTE STOPPAGES between Plumbridge Drive & Bath Rd./Durham Rd.  7 AM - 3 PM.

7/16/17-8/18/17

Durham Rd., Bristol Twp.

Roadwork: CLOSED & DETOURED between PA 413 & New Falls Rd. 8 PM - 5 AM.  DETOUR POSTED.

7/16/17-8/18/17

Ridge Rd., West Rockhill Twp., Perkasie Bor.

Milling & Paving: LANE RESTRICTIONS between County Line Rd. & Park Ave.  8 AM - 4 PM.

7/17/17-8/18/17

US 13 N & S, (Bristol Pike), Bristol Twp.

Storm Pipe Installation: LANE RESTRICTIONS between Haunted Lane & Cedar Ave.  Weekdays.  9 AM - 3 PM.

7/10/17-9/10/17

State Rd., Bristol Twp.

Utility Installation: LANE RESTRICTIONS between Wyoming Ave. & Bellevue Ave.  Weekdays.  9 AM - 3 PM. 

6/26/17-8/25/17

N. Main St., Sellersville Bor.

Culvert Replacement: CLOSED & DETOURED between Longwood Ave. & Twelfth St.  24-HOUR DETOUR.  DETOUR POSTED.

5/30/17-9/1/17

Lower State Rd., Doylestown Twp.

Multi-Use Trail Installation: LANE RESTRICTIONS between US 202 & Memorial Drive.  Weekdays.  9 AM - 3 PM.

5/30/17-10/17/17

US 13 N & S, (Bristol Pike), Bristol, Bensalem twps.

Milling & Paving: LANE RESTRICTIONS between Newportville Rd. & PA 413 (Veterans Hwy.)  Weekdays.  7 PM - 5 AM.

3/23/17-8/31/17

Mill Rd., Bensalem Twp.

Utility Installation: CLOSED & DETOURED between US 13 (Bristol Pike) & State Rd.  Weekdays.  9 AM - 3 PM.  DETOUR POSTED.

2/27/17-8/31/17

Steinsburg Rd., Milford Twp.

Bridge Replacement: CLOSED & DETOURED between Hieter Rd. & Wentz Rd.  24-HOUR DETOUR.  DETOUR POSTED.

2/27/17-11/10/17

Trumbauersville Rd., Milford Twp.

Bridge Replacement: CLOSED & DETOURED between Canary Rd. & Esten Rd.  24-HOUR DETOUR.  DETOUR POSTED.

2/27/17-11/10/17

PA 152 (Limekiln Pike), Warrington, Twp.

Utility Installation & Paving: CLOSED & DETOURED between Westminster Drive & County Line Rd.  24-HOUR DETOUR.  DETOUR POSTED.

12/13/16-10/12/17

County Line Rd., Warrington, Horsham, Montgomery twps.

Utility Installation: LANE RESTRICTIONS between East Kulp Rd. & Stump Rd.  7 AM - 3 PM.

3/7/16-9/2018

*US 202 North, Buckingham Twp., Doylestown Bor.

Road Construction: LANE RESTRICTIONS between PA 313 (Swamp Rd.) & Mechanicsville Rd.  9 AM - 3 PM.

4/13/15-11/9/18

*PA 263 (York Rd.), Warwick Twp.    

Road Reconstruction: LANE CLOSURES between Bristol Rd. & Sugar Bottom Rd.  24-HOUR RESTRICTIONS.

3/17/14-10/2017

Headquarters Rd., Tinicum Twp.

Bridge Damage: CLOSED & DETOURED between Red Hill Rd. & Tankhannen Rd.  DETOUR POSTED.

3/2/11-Indef.

 

MONTGOMERY COUNTY

 

 

*I-76 E & W, West Conshohocken Bor., Lower Merion Twp.

Milling & Concrete Patching: LANE CLOSURES between I-476 & US 1 (City Ave.)  9 PM - 9 AM.

8/12/17-8/13/17

*US 202 N & S (DeKalb Pike), Norristown

Utility Installation: LANE CLOSURES between Main St. & Schuylkill Ave.  8 PM - 6 AM.

8/13/17-8/18/17

Crooked Lane, Upper Merion Twp.

Base Repair: CLOSED & DETOURED between Yerkes Rd. & Crooked Lane intersection  & South Gulph Rd.  7 PM - 5:30 AM.  DETOUR POSTED.

8/13/17

*I-76 E & W, West Conshohocken Bor., Lower Merion Twp.

Milling & Concrete Patching: LANE CLOSURES between I-476 & US 1 (City Ave.)  9 PM - 5 AM.

8/13/17-8/18/17

*I-476 North, West Conshohocken Bor.

Bridge Inspection: RIGHT LANE CLOSED between I-76 & Ridge Pike Interchanges.  9 AM - 3 PM.

8/14/17

Swamp Creek Rd., Marlborough Twp.

Pipe Replacement: CLOSED & DETOURED between White Mills Rd. & Knuckles Rd.  7 AM - 3 PM.  DETOUR POSTED.

8/14/17

*US 422 West, Upper Providence, Lower Providence twps.

Concrete Patching: RIGHT LANE CLOSURE between Egypt Rd. & PA 363 (Trooper Rd.).  9 AM - 3 PM.

8/14/17-8/15/17

*US 422 E & W, Upper Merion, West Norriton twps.

Construction: LANE CLOSURES between Oaks and US 202 interchanges. Westbound 9 PM - 6 AM & Eastbound 7 PM - 5 AM.

8/14/17-8/17/17

*I-476 N & S, Lower Merion Twp, Conshohocken Bor.

ITS Fiber Installation: SHOULDER CLOSURE between I-76 & I-95.  9 AM - 3 PM.

8/14/17-8/18/17

Wynnewood Rd., Lower Merion Twp.

Trench Restoration: LANE RESTRICTIONS between Yerkes Rd. & Williams Rd.  8 AM - 4 PM.

8/14/17-8/17/17

*I-476 N & S, Plymouth, Lower Merion twps., West Conshohocken Bor.

Litter & Debris Removal: MOVING OPERATION WITH LANE CLOSURES between Turnpike/I-276 interchange & County Line Rd.  9 AM - 3 PM.

8/14/17-8/17/17

*I-76 E & W, Upper Merion, Lower Merion twps., West Conshohocken Bor.

Litter & Debris Removal: MOVING OPERATION WITH LANE CLOSURES between I-276 (PA Turnpike) & US 1 (City Ave.).  9 AM - 3 PM.

8/14/17-8/17/17

*US 422 E & W, Lower Providence, Upper Providence, Limerick, Lower Pottsgrove, North Coventry twps.

Litter & Debris Removal: MOVING OPERATION between PA 100 (Pottstown Pike) & PA 363 (Trooper Rd.).  9 AM - 3 PM.

8/14/17-8/17/17

Grosstown Rd., West Pottsgrove Twp.

Utility Installation: LANE RESTRICTIONS between Manatawny St. & Roberts Drive.  9 AM - 3 PM.

8/14/18-8/18/17

Flint Hill Rd., Upper Merion Twp.

Sidewalk Installation: LANE CLOSURE between Brentwood Court & Hertzog Blvd.  9 AM - 3 PM.

8/14/17-8/18/17

Norristown, Upper Providence, Lower Providence, Limerick, Whitemarsh twps.

Line Painting: SLOW MOVING OPERATION TO PAINT TRAFFIC LINES.  MOTORISTS ARE ADVISED TO REMAIN AN AMPLE DISTANCE BEHIND THE PAINTING TRUCK & STAY OFF TRAFFIC LINES.  9 AM - 3 PM.

8/14/17-8/18/17

PA 29 (Gravel Pike), Skippack Twp.

Paving Repairs: SINGLE LANE PATTERNS WITH 15-MIN. STOPPAGES between Main St. & PA 73 (Skippack Pike).  9 PM - 5 AM. 

8/14/17-8/18/17

Black Rock Rd., Upper Providence Twp.

Milling & Paving: LANE RESTRICTIONS between Collegeville Rd. & Troutman Rd.  Weekdays.  9 AM - 3 PM.

8/14/17-8/18/17

PA 73 (Skippack Pike), Skippack Twp.

Paving, Shoulder Back-Up, Guiderail: LANE RESTRICTIONS between Squirrel Hill Rd. & Perkiomen Creek Rd.  9 AM - 3 PM.

8/14/17-8/18/17

PA 29 (Gravel Pike), Perkiomen Twp.

Pole Relocations & Storm Sewer Installation:  LANE RESTRICTIONS between Miller Rd. & Harrison Ave.  9 AM - 3 PM.

8/14/17-8/18/17

Meyers Rd., Perkiomen Twp.

Water Line & Storm Sewer Installation: LANE RESTRICTIONS between Seitz Rd. & Miller Rd.  9 AM - 3 PM.

8/14/17-8/18/17

PA 611 (Old York Rd.), Abington Twp.

Bridge Work: LANE RESTRICTIONS between Jericho Rd. & Hamilton Ave.  9 AM - 3 PM.

8/14/17-8/18/17

Township Line Rd., Whitpain, East Norriton twps.

Test Holes: LANE RESTRICTIONS between Kimberly Drive & Oak Drive.  9 AM - 3 PM.

8/14/17-8/18/17

*US 202 N & S (DeKalb Pike), Whitpain Twp.

Test Holes: LANE RESTRICTIONS between PA Turnpike & Township Line Rd.    9 AM - 3 PM.

8/14/17-8/18/17

*US 202 N & S (DeKalb Pike), Whitpain Twp.

Test Holes: LANE RESTRICTIONS between PA 73 (Skippack Pike) & Cherry Lane.  9 AM - 3 PM.

8/14/17-8/18/17

Township Line Rd., Whitpain, East Norriton twps.

Test Holes: LANE RESTRICTIONS between Swede Rd. & DeKalb Pike.  9 AM - 3 PM.

8/14/17-8/18/17

Norristown Rd., Lower Gwynedd Twp.

ITS Installation: LANE CLOSURES between Bethlehem Pike & Tennis Ave.  9 AM - 3 PM.

8/14/17-8/18/17

Germantown Pike, East Norriton, Plymouth twps.

ITS Installation: LANE CLOSURES between I-476 & Swede Rd.  9 AM - 3 PM.

8/14/17-8/18/17

PA 63 (Sumneytown Pike), Lower Salford, Towamencin, Upper Gwynedd, Lower Gwynedd, Montgomery twps.; North Wales Bor.

ITS Installation: LANE CLOSURES between Harleysville Pike & Bethlehem Pike.  9 AM - 3 PM.

8/14/17-8/18/17

Bethlehem Pike, Montgomery, Hatfield twps.

ITS Installation: LANE CLOSURES between McLaughlin Rd. & Bergey Rd.  9 AM - 3 PM.

8/14/17-8/18/17

N. Adams St., Pottstown Bor.

ADA Ramp Construction: LANE CLOSURE at Wilson St./Jackson St.  9 AM - 3 PM.

8/14/17-8/18/17

High St., Pottstown Bor.

ADA Ramp Construction: LANE CLOSURE at Roland St./Park Blvd. & Keim St.  9 AM - 3 PM.

8/14/17-8/18/17

High St., Pottstown Bor.

ADA Ramp Construction: LANE CLOSURE between Roland St. & Park Blvd.  9 AM - 3 PM.

8/14/17-8/18/17

Wilson St., Pottstown Bor.

ADA Ramp Construction: LANE CLOSURE at N. Hanover St.  9 AM - 3 PM.

8/14/17-8/18/17

Main St. East Greenville Bor.

Utility Installation: LANE CLOSURE between Church St. & Front St.  9 AM - 3 PM.

8/14/17-8/21/17

*I-476 North, West Conshohocken Bor.

Bridge Inspection: RIGHT LANE CLOSED between I-76 & Ridge Pike Interchanges.   9 AM - 3 PM.

8/15/17

Stump Hall Rd., Worcester Twp.

Base Repair: CLOSED & DETOURED between PA 363 (Valley Forge Rd.) & Hollow Rd.  7 PM - 5:30 AM.  DETOUR POSTED.

8/15/17

Schoolhouse Rd., Franconia Twp.

Trench Restoration: LANE RESTRICTIONS between Wambold Rd. & Skippack Creek Rd.  9 AM - 3 PM. 

8/15/17-8/16/17

*US 422 East, Lower Pottsgrove Twp.

Roadway Maintenance: RIGHT LANE CLOSED between PA 724 (Schuylkill Rd.) & Sanatoga interchanges.  9 AM - 2 PM.

8/15/17-8/16/17

E. High St., Lower Pottsgrove Twp.

Utility Installation: LANE RESTRICTIONS between Hause Ave. & Brown St.  9 AM - 3 PM.

8/15/17-8/16/17

US 202 North (DeKalb Pike), Upper Merion Twp.

Telephone Pole Replacement: RIGHT LANE CLOSED between King Circle & Town Centre Rd.  9 AM - 3 PM.

8/16/17

*I-476 North, West Conshohocken Bor.

Bridge Inspection: LEFT LANE CLOSED between I-76 & Ridge Pike Interchanges.  9 AM - 3 PM.

8/16/17

Gilbertsville Rd., Douglass, Upper Pottsgrove twps.

Base Repair: CLOSED & DETOURED between Grosser Rd./Thrush Dr. & Farmington Ave.  7 PM - 5:30 AM.  DETOUR POSTED.

8/16/17-8/17/17

*US 422 East, Upper Providence, Lower Providence twps.

Concrete Patching: LEFT LANE CLOSURE between Egypt Rd. & PA 363 (Trooper Rd.).  9 AM - 3 PM.

8/16/17-8/17/17

*I-476 South, West Conshohocken Bor.

Bridge Inspection: LEFT LANE CLOSED between Ridge Pike & I-76 Interchanges.  9 AM - 3 PM.

8/17/17

E. First Ave., Trappe Bor.

Utility Installation: LANE RESTRICTIONS between College Ave. & W. Main St.  9 AM - 3 PM.

8/17/17-8/18/17

PA 152 (Limekiln Pike), Abington, Cheltenham twps.

Test Holes: LANE SHIFT between Mt. Carmel Ave. & Roosevelt Ave.  9 AM - 3 PM. 

8/17/17-8/18/17

PA 29 South (Gravel Pike), Lower Fredrick Twp.

Bridge Inspection: RIGHT LANE CLOSED between Memorial Drive & Delphi Rd.  9 AM - 3 PM.

8/18/17

Bleim Rd., Lower Pottsgrove Twp.

Base Repair: CLOSED & DETOURED between North Pleasantview Rd. & Kepler Rd.  7 PM - 5:30 AM.  DETOUR POSTED.

8/18/17

*I-76 E & W, West Conshohocken Bor., Lower Merion Twp.

Milling & Concrete Patching: LANE CLOSURES between I-476 & US 1 (City Ave.)  9 PM - 9 AM.

8/19/17-8/20/17

Susquehanna Rd., Abington Twp.

Utility Installation: LANE CLOSURE between Westmont Ave. & Johnston Ave.  Weekdays.  9 AM - 3 PM.

8/22/17-8/29/17

Dreshertown Rd., Upper Dublin Twp.

Utility Installation: LANE CLOSURE between Caras Ct. & Crestview Drive.  Weekdays.  9 AM - 3 PM.

8/24/17-8/31/17

Church Rd., Cheltenham Twp.

Utility Installation: CLOSED & DETOURED between Washington Lane & York Rd.  Weekdays.  9 AM - 3 PM.  DETOUR POSTED.

8/24/17-12/29/17

South Gulph Rd., Upper Merion Twp.

Utility Installation: LANE CLOSURE between Brooks Rd. & Croton Rd.  Weekdays.  9 AM - 3 PM.

8/28/17-8/31/17

Stenton Ave., Whitpain Twp.

Surface Treatment: LANE RESTRICTIONS at Narcissa Rd. & Norristown Rd.  Weekdays.  9 AM - 3 PM & Saturday 7 AM - 5 PM.

8/7/17-8/12/17

Whitehall Rd., Worcester Twp.

Surface Treatment: LANE RESTRICTIONS between Bean Rd. & Skippack Pike.  9 AM - 3 PM & Saturday 7 AM - 5 PM.

8/7/17-8/12/17

Pleasant View Rd., Lower Pottsgrove Twp.

Surface Treatment: LANE RESTRICTIONS between Foxtail Drive & N. Sanatoga Rd.  Weekdays.  9 AM - 3 PM.  Saturday. 7 AM - 5 PM.

8/7/17-8/12/17

Cowpath Rd., Montgomery Twp.

Utility Installation: LANE CLOSURE between Taylor Rd. & Tanglewood Drive.  Weekdays.  9 AM - 3 PM.

8/7/17-8/14/17

Wambold Rd., Lower Salford Twp.

Utility Installation: LANE CLOSURE between Cassell Rd. & Pretz Rd.  Weekdays.  9 AM - 3 PM.

8/7/17-8/14/17

US 30 (Lancaster Ave.), Lower Merion Twp.

Conduit Installation: LANE RESTRICTIONS between Tenmoe Rd. & N. Buck Lane.  Weeknights.  7 PM - 5 AM.

8/7/17-8/18/17

PA 63 E & W (Welsh Rd./Moreland Rd.), Abington, Upper Moreland twps.

Manhole & Inlet Adjustments:  PERIODIC LANE RESTRICTIONS between Fitzwatertown Rd. & Edge Hill Rd.  Weeknights.  7 PM - 5 AM.

8/7/17-8/31/17

Norristown Rd., Upper Dublin Twp.

Utility Installation: LANE CLOSURE between Clinton Drive & Tally Ho Drive.  9 AM - 3 PM.

8/10/17-8/17/17

S. Lewis Rd., lUpper Providence Twp.

Utility Installation: LANE CLOSURE between Becthel Rd. & Canci Ct.  9 AM - 3 PM. 

8/10/17-8/17/17

PA 63 (Sumneytown Pike), Towamencin Twp.

Core Boring: LANE RESTRICTIONS between Mainland Rd. & Pa Turnpike/I-476.  9 AM - 3 PM.

8/11/17-8/18/17

Creamery Rd., Franconia Twp.

Conduit Installation: LANE RESTRICTIONS between Freed Rd. & Kulp Rd.  Weekdays.  9 AM - 3 PM.

7/31/17-8/25/17

Radnor Street Rd., Upper Merion Twp.

Utility Installation: CLOSED & DETOURED between Croton Rd. & Springbrook Lane.  Weekdays.  9 AM - 3 PM.  DETOUR POSTED.

8/2/17-9/1/17

Belmont Ave., Lower Merion Twp.

Utility Installation: CLOSED & DETOURED between Rockhill Rd. & US 1 (City Ave.).   Weekdays.  9 AM - 3 PM.  DETOUR POSTED.

7/24/17-8/18/17

PA 113 W & W (Harleysville Pike/Main St.), Franconia Twp., Souderton Bor.

Milling & Paving:  LANE RESTRICTIONS between PA 63 (Sumneytown Pike) & Broad St.  Weeknights.  7 PM - 5 AM.

7/24/17-8/31/17

PA 63 (Welsh Rd.), Abington, Lower Moreland twps.

Milling & Paving: CLOSED AND DETOURED between Edge Hill Rd. & Terwood Rd. 9 AM - 3 PM. DETOUR POSTED.

7/24/17-8/2017

North Trooper Rd., Lower Providence Twp.

Utility Installation: LANE RESTRICTIONS between Lloyd Ave. & Ridge Pike. Weekdays.   9 AM - 3 PM.

7/25/17-8/25/17

PA 29 (Collegeville Rd.), Upper Providence Twp.

Milling & Paving: LANE RESTRICTIONS between Hasson Rd. & Town Center Drive.  Weekdays.  9 AM - 3 PM.

7/26/17-8/11/17

PA 363 (Trooper Rd.), Lower Providence Twp.

Road Widening & Utility Installation: LANE RESTRICTIONS between Eisenhower Ave. & Shannondell Blvd.  Weeknights.  7 PM - 5 AM.

7/17/17-11/30/17

Orvilla Rd., Hatfield Twp.

Utility Installation: CLOSED & DETOURED between Cowpath Rd. & County Line Rd.  Weeknights.  7 PM - 5 AM.  DETOUR POSTED.

7/10/17-9/10/17

Matsonford Rd., Upper Merion, Lower Merion twps.

Bridge Repair: CLOSED & DETOURED between Montgomery Ave. & Old Gulph Rd.  Weekdays.  9 AM - 3 PM.  DETOUR POSTED.

7/10/17-10/10/17

PA 23 ramp to US 422 East, Upper Merion, West Norriton twps.

Ramp Reconstruction:  RAMP CLOSED & DETOURED.  24-HOUR DETOUR.  DETOUR POSTED. 

7/10/17-11/2017

Terwood Rd., Upper Moreland Twp.

Bridge Rehabilitation: CLOSED & DETOURED between York Rd. & Davisville Rd.  24-HOUR DETOUR.  DETOUR POSTED.

7/5/17-8/18/17

PA 63 (Welsh Rd.), Upper Dublin, Upper Moreland twps.

Deck Rehabilitation: LANE CLOSURES between Twining Rd. & Computer Ave.  Weekdays.  9 AM - 3 PM.

7/6/17-9/30/17

PA 663 (Layfield Rd.), Upper Hanover Twp.

Bridge Replacement: CLOSED & DETOURED between Kutztown Rd. & Hill Rd.  24-HOUR DETOUR.  DETOUR POSTED.

6/19/17-8/31/17

New Second St., Cheltenham Twp.

Bridge Reconstruction: CLOSED & DETOURED between Ashbourne Rd. & Church Rd.  24-HOUR DETOUR.  DETOUR POSTED.

6/21/17-9/4/17

W. Wynnewood Rd, Lower Merion Twp.

Utility Installation: LANE RESTRICTIONS between E. County Line Rd. & Ballytore Rd.  Weekdays.  9 AM - 3 PM.

6/5/17-9/22/17

Hollow Rd., Lower Merion Twp.

Utility Installation: LANE RESTRICTIONS between PA 23 (Conshohocken State Rd.) & Hagys Ford Rd.  Monday thru  Saturday.  9 AM - 3 PM.

6/9/17-8/25/17

Buchert Rd., Pottsgrove Twp.

Curb Ramp Construction: LANE CLOSURE at Pleasantview Rd.; N. Washington St. & Mervine St.  9 AM - 3 PM.

5/30/17-8/18/17

Mervine St., Lower Pottsgrove Twp, Pottstown Bor.

Curb Ramp Construction: LANE CLOSURE at N. Franklin St.  9 AM - 3:30 PM.

5/30/17-8/18/17

Susquehanna Rd., Abington Twp.

Utility Installation: CLOSED & DETOURED between Washington Lane & Rydal Rd./Valley Rd.  Weekdays.  9 AM - 3 PM.  DETOUR POSTED.

5/23/17-8/28/17

Plank Rd., Perkiomen Twp.

Excavation/Grading/Paving: CLOSED & DETOURED between PA 29 (Gravel Pike) & PA 73 (Skippack Pike).  24-HOUR DETOUR.  DETOUR POSTED.

5/2/17-10/2017

Otts Rd., Perkiomen Twp.

Excavation/Grading/Paving: CLOSED & DETOURED between Miller Rd. & PA 29 (Gravel Pike).  24-HOUR DETOUR.  DETOUR POSTED.

5/2/17-5/2019

PA 63 (Main St.), Lower Salford Twp.

Roadway & Culvert Widening: LANE RESTRICTIONS between PA 113 (Harleysville Pike) & Carrie Lane.  Weekdays.  9 AM - 3 PM.

3/15/17-11/1/17

*US 422 East, Lower Pottsgrove Twp.

Road & Bridge Construction: LANE CLOSURES between PA 724 (Schuylkill Rd.) & Sanatoga Interchanges.  5 PM - 5 AM.

1/23/17-10/29/17

*US 422 West, Lower Pottsgrove Twp.

Road & Bridge Construction: WEEKEND LANE CLOSURES between Sanatoga & PA 724 (Schuylkill Rd.) Interchanges.  7 PM - 1 PM.

1/23/17-10/29/17

Edge Hill Rd., Abington Twp.

Bridge Rehabilitation: CLOSED & DETOURED between Ferndale Ave. & Hamilton Ave.  24-HOUR DETOUR.  DETOUR POSTED.

1/9/17-11/1/17

East Walnut St., Hatfield Twp.

Bridge Replacement: CLOSED & DETOURED between PA 309 & County Line Rd.  24-HOUR DETOUR.  DETOUR POSTED.

10/24/16-9/28/17

County Line Rd., Warrington, Horsham, Montgomery twps.

Utility Installation: LANE RESTRICTIONS between  Kulp Rd. & Stump Rd.  7 AM - 3 PM.

3/7/16-9/2018

Baligomingo Rd., West Conshohocken Bor.

Slope Stabilization: CLOSED & DETOURED between PA 23 (Front St.) & Portland Rd.  24-HOUR DETOUR.  DETOUR POSTED.

6/27/15-Indef.

PA 724 ramp to US 422 East, Lower Pottsgrove Twp.

Roadwork: RAMP CLOSED & DETOURED.  24-HOUR CLOSURE.  DETOUR POSTED.

5/27/15-3/2018

*US 422 E & W, Lower Pottsgrove Twp.

Road Construction: TRAFFIC PATTERN SHIFT between Sanatoga & PA 724 (Schuylkill Rd.) Interchanges.  24-HOUR PATTERN.

2/2/13-8/2018

*US 422  E & W, West Pottsgrove Twp.

Bridge Construction: REDUCED TO ONE LANE between Stowe & PA 100 Interchange.  24-HOUR RESTRICTION.

11/27/14-9/2018

County Line Rd., Upper Merion Twp.

Road Work: CLOSED & DETOURED WEEKDAYS between PA 23 & Gulph Rd. 7 AM Mondays thru 5 PM Fridays.  24-HOUR CLOSURE. DETOUR POSTED.

5/9/14-12/29/17

 

 (* DENOTES DELAYS ARE EXPECTED)

 

 

A Special Thanks to Our Sponsors