ROUTE 309 IMPROVEMENT PROJECT WEEKLY ACTIVITY AND LANE RESTRICTIONS For Week of 5/12/08 to 5/19/08
R. 0309, Section 101 & 104 (Highland Avenue to Welsh Road (Route 63)) Dates: 5/5/08 – 5/12/08 Hours: 9:00AM to 3:00PM and 9:00PM to 5:00AM Weather Dependent: Yes Description of Work: Section 101 Roadwork related to reconstruction of the expressway in Upper Dublin and Lower Gwynedd townships. Structure work to replace or rehabilitate existing bridges. Section 104 is the ITS (Intelligent Transportation System) Project Location of Restriction: SR 309 from English Village Road to Highland Avenue. Side roads , Bethlehem Pike SR 309, McKean Road SR 309, Susquehanna Road SR 309, Cedar Hill Road SR 309, Butler Pike SR 309, Tennis Avenue SR 309, Loch Alsh Avenue SR 309. Butler Pike off ramp on SB 309 and Susquehanna Road on ramp to SB 309 remain closed. Cedar Hill Road Bridge over SR 309 remains closed. Detour signs are in effect. McKean Road and Tennis Avenue are reduced to a single lane at SR 309 until further notice. Traffic signals are in effect. Southbound Route 309 is reduced to a single lane for the duration of the project from Bethlehem Pike to Norristown Road. Section 104 work is currently on SR 309 from Welsh Road to Cowpath Road and will have minimal lane restrictions. Type of Restriction: .:. Off peak day and night lane closures may occur at various locations. Welsh Road (SR 63) at both approaches to SR 309 may be impacted with lane restrictions starting Monday, May 12 .:. SB 309 may be reduced to one lane between 9:00am and 3:00pm between English Village Road and Welsh Road .:. During off peak day hours there will be a lane closure NB 309 to do repairs on the Loch Alsh Bridge just north of the Highland Avenue exit. The day and time has yet to be determined.
R. 0309, Section 102 (Easton Road Interchange and Southern Portion of S. R. 0309) Dates: 5/12/08 – 5/17/08 Hours: 9:00AM to 3:00PM Weather Dependent: Yes Description of Work: Sawing / sealing, concrete curb and sidewalk, install attenuator at 2+814, remove temporary barrier Location of Restriction: Route 309 - Cheltenham Avenue to Easton Road Type of Restriction: R. 0309 Northbound and Southbound - Restrictions as needed
R. 0309, Section 102 (Easton Road Interchange and Southern Portion of S. R. 0309) Dates: 5/12/08 – 5/17/08 Hours: 9:00AM to 3:00PM Weather Dependent: Yes Description of Work: Paving (finished / wearing) Location of Restriction: Route 309 - from Cheltenham Avenue to Easton Road Type of Restriction: Limited access - 2000 to 2100 restricted access from 2100 to 0500 - on Route 309
R. 0309, Section 102 (Easton Road Interchange and Southern Portion of S. R. 0309) Dates: 5/12/08 – 5/17/08 Hours: 9:00AM to 3:00PM Weather Dependent: Yes Description of Work: Remove temporary barrier, class I excavation , drainage, subbase, install subbase wall panel painting and install , bridge construction Location of Restriction: Easton Road - from Easton Road to Haws Lane Type of Restriction: R. 0309 Northbound and Southbound - Restrictions as needed
R. 0309, Section 102 (Easton Road Interchange and Southern Portion of S. R. 0309) Dates: 5/12/08 – 5/17/08 Hours: 9:00AM to 3:00PM Weather Dependent: Yes Description of Work: Saw and seal curb , mountable curb and sidewalk Location of Restriction: Easton Road - from Cheltenham Avenue to Route 73 Type of Restriction: Lane restrictions as needed
R. 0309, Section 103 (Ft. Washington Interchange) Dates: 5/12/08 – 5/17/08 Hours: 9:00AM to 3:00PM Weather Dependent: Yes Description of Work: Safety improvement and general reconstruction of Route 309 in Fort Washington Location of Restriction: R. Northbound and Southbound - between Route 73 (Church Road) and Highland Avenue Type of Restriction: S. R 0309 Northbound and Southbound - Possible daytime single lane closures by Nyleve / JDM Joint Venture CMS #64275
|
|||||